Wastewater
Lago Vista may cut Garver sewer plant deal by $1,248,133.90
Council votes Nov. 5 on cutting the Garver sewer plant contract to $1,573,768.10. A federal grant would pay most of the new design work.
The Lago Vista City Council will vote Nov. 5, 2026, on cutting its sewer plant engineering contract with Garver, LLC from $2,821,902.00 to $1,573,768.10. The change drops the design for a bigger plant and frees $1,248,133.90 that the city would no longer owe. A federal Environmental Protection Agency (EPA) grant would pay up to $488,799.20 of the new design work, and the city would pay $122,199.80 as its required share. The city would pay another $354,278.00 outside the grant, for construction administration and observation. Staff recommend that the council approve it.1
Listen
AI voices
A two-host briefing. The voices are AI generated. Read the transcript.

What is the Garver contract?
Garver, LLC is the engineering firm the city hired to design work at its wastewater treatment plant. The plant treats the city's sewage, and the first plan was to grow it from 1.0 million gallons a day (MGD) to 1.5 MGD. The contract has a not-to-exceed amount, which is the most the city can owe the firm. The council decides whether to approve this change, and if it does, the city manager signs it.1
Victor Manzano, the city's capital improvement plan (CIP) manager, submitted the item, and the packet does not say who asked for it. The council's regular meeting starts at 3 p.m. in the City Council Chambers, 5803 Thunderbird. The agenda lists a closed executive session first and says the regular session will reconvene at 4 p.m.1
Our earlier story about the city's state loan for the plant told how the contract began. It left open why the project moved from expansion to repair.
On May 16, 2024, the City Council voted unanimously to pick Garver to design a plant upgrade to 1.5 MGD.2 On Dec. 5, 2024, the council approved a contract with Garver for the design, at no more than $2,821,902.00.3 The contract is dated Dec. 11, 2024, and a first amendment followed on May 2, 2025.1 In October 2025 the council tabled a proposed amendment of up to $1,864,090.00 by a vote of 7 to 0.4
What changed before Nov. 5
The packet says the city weighed plant conditions, operating priorities, and project costs, and then shifted its near-term project away from an expansion. It says the council earlier told staff to move the filters and dewatering press ahead on their own, and to study a mechanical bar screen and grit chamber before going further.1
On Sept. 17, 2026, Mayor Saum said the "unencumbered amount" of the city's 2024 bond was "somewhere around $2.2 million." Saum asked the council to set that money aside for a Type 1 filter. Another speaker answered that the EPA grant request covered several improvements, so a change would mean redoing that document.5 The packet now refers to a revised EPA grant workplan that lets the grant pay for eligible planning, permitting, design, and bid-phase services.1 The packet does not say whether the mayor's request led to that revision.
What Amendment No. 2 would do
Amendment No. 2 splits the contract into two parts. Part 1 closes the original design work at $608,491.10, which is what Garver had billed through Aug. 29, 2025. Of the $2,213,410.90 not yet billed under the old contract, $965,277.00 would move to Part 2.1
Part 2 covers a packaged tertiary filter system and a new volute press. Garver would design the filters and apply to the Texas Commission on Environmental Quality (TCEQ) for a Type I permit to reuse treated water. The new press would replace the existing belt filter press inside the existing dewatering building. The packet expects no structural changes to that building.1
The filters and the press would go out for bids as two packages at different times. The amendment also leaves out the mechanical bar screen and grit chamber for more study. No construction contract is part of this vote. Future construction contracts would come back to the council separately.1
Who pays
The grant budget counts $610,999.00 of the $965,277.00 in new work. Construction administration and observation are not grant costs. Those two tasks are priced at $219,558.00 and $134,720.00.1
Certificates of obligation are city debt, and the packet for the 2024 sale said they were payable from a property tax on all taxable property in the city and a limited pledge of water and sewer revenue.6 Staff recommend paying the city's share from 2024 Certificate of Obligation bond proceeds, Utility Reserves, or both. The packet says that choice is "subject to confirmation of available balances and final budget allocation."1
Wastewater impact fees were first named as a possible source for this project, and staff no longer recommend them.1 The adopted 2026-27 budget's capital plan still lists $820,000 in wastewater impact fees as the source for this project's design work that year.7
Other items on the same agenda
Item VIII.1 asks for approval of a $216,975 effluent master plan, a study of how the city handles treated wastewater. The EPA grant would pay $173,580 of it, and the city's required match is $43,395. Item VIII.3 is a vote on the city's part in the state loan program for the plant improvements project. A work session item the same day covers how to divide the EPA Community Grant between the plant and effluent projects.1
What it means for you
This vote sets the most Garver can bill for engineering services, not what the plant work will cost to build.1 In Oct. 2025, a Garver presenter said tertiary filters were "in the 4 to 5 million range" to build.8 If the council approves, the City Manager may sign the amendment, subject to "final legal review and applicable grant requirements."1
What we could not find
- The outcome of the vote, who moves and seconds the motion, and how each member votes. The video and minutes are not posted yet.
- What the first amendment changed. It is not in this packet.
- Who decided to move from expansion to repair, and when. The packet says only that the city shifted its near-term project.
- What became of the Garver request that the council tabled.
- The revised EPA grant workplan and the grant's total. The packet gives only the shares that apply to this contract.
- Whether the city's share would come from the unencumbered bond money the mayor described in September, and the current balances of that bond and of utility reserves.
- What Garver has billed since the last invoice the amendment names, and whether the capped amount matches paid invoices.
- A construction cost for the revised project.
What you can do
- To speak in person, fill out the form in the chambers and give it to the mayor before the meeting starts. To speak online, email the form as it instructs.1
- Ask the city for the missing records under the Texas Public Information Act. The city's open records page says it has up to 10 business days to respond.9
Email alerts
Get the next story by email
We email you when a person has checked a new story against the record and it goes live. No ads, no tracking.
Lago Vista Watchdog is free for everyone. Readers who can pay keep it that way. Become a member.
Podcast transcript
Read the transcript
Host 1. This is the Lago Vista Watchdog briefing. The two voices you are hearing are AI generated. Every fact in this episode is sourced in the full story on our website, and a person validates each story before it is published.
Host 2. Here is the bottom line. On November 5, 2026, the Lago Vista City Council will vote on cutting its sewer plant engineering contract with Garver, LLC from 2,821,902 dollars to 1,573,768.10 dollars. The vote has not happened yet. According to the city's packet, the change drops the design for a bigger plant and frees 1,248,133.90 dollars that the city would no longer owe.
Host 1. A federal Environmental Protection Agency grant, called the EPA grant, would pay up to 488,799.20 dollars of the new design work. The city would pay 122,199.80 dollars as its required share. The city would pay another 354,278 dollars outside the grant, for construction administration and observation. Staff recommend that the council approve it.
Host 2. Some background. Garver is the engineering firm the city hired to design work at its wastewater treatment plant. The plant treats the city's sewage, and the first plan was to grow it from 1.0 million gallons a day to 1.5 million gallons a day. The contract has a not-to-exceed amount, which is the most the city can owe the firm. The council decides whether to approve this change, and if it does, the city manager signs it.
Host 1. Now, in order. Our earlier story on the state loan for the plant told how the contract began. On May 16, 2024, the council voted unanimously to pick Garver to design a plant upgrade to 1.5 million gallons a day. On December 5, 2024, the council approved a contract with Garver at no more than 2,821,902 dollars.
Host 2. The contract is dated December 11, 2024, and a first amendment followed on May 2, 2025. In October 2025 the council tabled a proposed amendment of up to 1,864,090 dollars, by a vote of 7 to 0.
Host 1. What changed since? The packet says the city weighed plant conditions, operating priorities, and project costs, and then shifted its near-term project away from an expansion. It says the council earlier told staff to move the filters and the dewatering press ahead on their own, and to study a mechanical bar screen and grit chamber before going further.
Host 2. On September 17, 2026, Mayor Saum said the unencumbered amount of the city's 2024 bond was somewhere around 2.2 million dollars. Saum asked the council to set that money aside for a Type 1 filter. Another speaker answered that the EPA grant request covered several improvements, so a change would mean redoing that document. The packet now refers to a revised EPA grant workplan.
Host 1. So what would Amendment Number 2 do? It splits the contract into two parts. Part 1 closes the original design work at 608,491.10 dollars, which is what Garver had billed through August 29, 2025. Of the 2,213,410.90 dollars not yet billed under the old contract, 965,277 dollars would move to Part 2.
Host 2. Part 2 covers a packaged tertiary filter system and a new volute press. Garver would design the filters and apply to the Texas Commission on Environmental Quality for a Type I permit to reuse treated water. The new press would replace the existing belt filter press inside the existing dewatering building. The filters and the press would go out for bids as two packages at different times.
Host 1. No construction contract is part of this vote. Future construction contracts would come back to the council separately.
Host 2. Who pays? The grant budget counts 610,999 dollars of the 965,277 dollars in new work. Construction administration and observation are not grant costs. Staff recommend paying the city's share from 2024 Certificate of Obligation bond proceeds, Utility Reserves, or both. The packet says that choice is subject to confirmation of available balances and final budget allocation.
Host 1. Certificates of obligation are city debt. The packet for the 2024 sale said they were payable from a property tax on all taxable property in the city and a limited pledge of water and sewer revenue. Wastewater impact fees were first named as a possible source, and staff no longer recommend them.
Host 2. What it means for you. This vote sets the most Garver can bill for engineering services, not what the plant work will cost to build. In October 2025, a Garver presenter said tertiary filters were in the 4 to 5 million range to build.
Host 1. What we could not find. The outcome of the vote, what the first amendment changed, who decided to move from expansion to repair, and the revised EPA grant workplan are not in the records we reviewed.
Host 2. How to weigh in. To speak in person, fill out the form in the chambers and give it to the mayor before the meeting starts. To speak online, email the form as it instructs. You can also ask the city for the missing records through its open records page. Thanks for listening to the Lago Vista Watchdog.
Sources and documents
Every fact in this story comes from the records below. The small numbers in the story point to them. Links go to the exact moment in the meeting video or the page in the document.
- Lago Vista City Council agenda packet, Nov. 5, 2026, item VIII.2 and Contract Amendment No. 2 with Garver, LLC
- City Council minutes, May 16, 2024
- City Council minutes, Dec. 5, 2024
- City Council minutes, Oct. 2, 2025
- City Council video, Sept. 17, 2026. The mayor asks to set aside 2024 bond money for a Type 1 filter, and another speaker answers At 1:31:59.
- City Council agenda packet, Jan. 18, 2024, certificates of obligation item See p. 21.
- City of Lago Vista 2026-27 budget, capital improvement plan page for WWTP Improvements See p. 172.
- City Council video, Oct. 2, 2025. A Garver presenter on the cost of tertiary filters At 1:39:40.
- City of Lago Vista open records request page
See something wrong? Request a correction. Have records on this? Share them with us.