Development
Lago Vista's Tessera PID bills drop $64,692.33 for 2027
Tessera owners owe $4,213,564.99 in PID bills due Jan. 31, 2027, $64,692.33 less than a year earlier. City taxes are not pledged to the 2024 bonds.
Property owners in Lago Vista's Tessera on Lake Travis public improvement district (PID) are scheduled to pay $4,213,564.99 in assessments, which are yearly charges on each lot, due Jan. 31, 2027. That is $64,692.33 less than the 2025 plan scheduled a year earlier.1 The City Council approved the 2026 plan that sets those bills by a 7-0 vote on Aug. 6, 2026.2 Tessera owners pay the bills, not the city's general taxpayers.3 The district's 2024 bonds "shall never be payable from ad valorem taxes or any other funds or revenues of the City."4
Listen
AI voices
A two-host briefing. The voices are AI generated. Read the transcript.

Totals, differences, and percentages in this story are our calculations from the cited plans.1
What is a PID?
A public improvement district (PID) lets a city take on a project that "confers a special benefit on a definable part of the municipality."5 Owners in the district pay yearly installments, which the city collects "in the same manner and at the same time as ad valorem taxes," meaning property taxes. The installments repay bonds, which are loans from investors, and in one area they also repay the developer.6 An assessment is a charge on a lot, and state law makes it "a first and prior lien against the property assessed," a legal claim on the property until it is paid. The service plan is the district's budget, and it must "cover a period of at least five years."5 State law requires the council to review and update the plan every year.1 P3Works, LLC is the district's administrator, the firm that prepares each year's plan.6 The district bills four parts separately, called Improvement Area #1, Area #2, Area #3, and the Major Improvement Area.1
Our earlier story on Tessera's PID covered the park-list motions at both meetings and the debate over what buyers are told.2 This story compares the dollar figures in the two plans.3
What did the 2025 plan bill?
The council took up the 2025 plan at a regular meeting in the City Council Chambers on Aug. 21, 2025, as item 11A.7 City Manager Charles West submitted the item. The cover page said the update documents the assessments "necessary for the tax roll" that must be approved before it goes to Travis County by Oct. 1.3 Sara Blasdell with P3Works presented the update, according to the minutes.7 On the video, she gave her name as a representative of P3Works and spelled it.8
The 2025 plan set the bill for Area #1 at $312,325.40 for the installment due Jan. 31, 2026. For 2026, it set Area #2 at $356,630.98. For 2026, it set Area #3 at $2,488,597.48. For 2026, it set the Major Improvement Area at $1,120,703.46. The four bills together came to $4,278,257.32. The cover page said, "There is no financial impact to the City."3
Mayor Kevin Sullivan moved to approve the ordinance, and Council Member Adam Benefield seconded.7 The motion added a new Exhibit B, a list of park facilities for the notices given to buyers, with items A and C removed.78 On the video, item A was described as starting with "approximately 6,840 linear feet," and item C with "the concrete ADA ramp." A speaker said those two items "technically have not been dedicated to the city yet."8 The motion as the minutes record it changed no dollar amount.7
The motion passed 6-1, with Mayor Pro Tem Rob Durbin voting no.7
What did the 2026 plan bill?
The council took up the 2026 plan at a regular meeting on Aug. 6, 2026, in the City Council Chambers at 5803 Thunderbird.2 West submitted this item too.1 A representative of P3Works presented the update, and the minutes do not name that person.2
The cover page lists the 2027 bill for Area #1 at $308,311.15 and Area #2 at $350,949.17. Area #3's bill is $2,433,516.59, and the Major Improvement Area's is $1,120,788.08. Under financial impact, the cover page puts "None." It warns that individual installments may be adjusted before billing for prepayments or bond redemptions.1
Mayor Pro Tem Norma Owen moved to approve the ordinance, and Council Member Amanda Chavarria seconded. The minutes word the motion as "Add attachment B, exclude what has not been approved."2 On the video, the chair said, "I have a motion from the Mayor Pro Tem," and then named "Councilor Chavarria" as the second.9
The motion as recorded names no change to a dollar amount.2 It passed 7-0, and on the video the vote is called "approved unanimously."9
How did the total bill change?
The 2026 plan puts the total for 2027 at $4,213,564.99. That is 1.5% less than the 2025 plan's total. Area #1's bill fell by $4,014.25. Area #2's bill fell by $5,681.81. Area #3's bill fell by $55,080.89. The Major Improvement Area's bill rose by $84.62.1
Why did Area #3's bill change?
The 2025 plan budgeted $105,771.48 in administrative costs for Area #3.3 The 2026 plan budgets $50,085.59 in administrative costs for Area #3. That is $55,685.89 less. The administrative costs fell by more than Area #3's whole bill did.1
One line in the 2025 list was for past-due invoices from P3Works, at $58,588.61. The plan labeled it "Past Due P3Worksc LLC Invoices."3 The 2026 Area #3 list we reviewed has no line like it.1 The plans we reviewed do not say which invoices were past due or for what years.3 Owners pay these costs "on a pro rata basis by each Parcel," based on the assessment left on the parcel. The 2026 Area #3 list includes $1,116.12 for the city auditor, which owners also pay.1
What does one Tessera home pay?
Every one of the 19 lot types has a smaller bill for 2027 than for 2026.13 Lot Type 14 is a 40-foot lot in Phase 2 of Area #3.6 For 2026, its bill was $4,799.22, including $169.02 as its share of Area #3 administrative costs.3 For 2027, its bill is $4,711.43, with $80.19 for those costs. That is $87.79 less. Its share of Area #3 administrative costs alone fell by $88.83. Over its schedule through 2054, a Lot Type 14 home's bills add up to $133,966.96. Of that, $30,689.34 is principal and $33,903.86 is interest on the developer's reimbursement. Together that is 48.2% of the home's scheduled bills.1
Lot Type 16 is a 60-foot lot in Phase 2.6 Its bill for 2026 was $6,126.66.3 Its bill for 2027 is $6,014.59. That is $112.07 less. In the older Areas #1 and #2, the 2027 bills run from $690.26 for Lot Type 1 to $1,598.23 for Lot Type 7. The plan calls these figures "estimates only and subject to change."1
Who gets paid?
The 2027 bills include $1,410,300 for the developer's reimbursement obligation. That is 33.5% of the total.1 The obligation repays the developer for costs it paid up front for Area #3 projects, plus interest.6 The 2026 plan charges that interest at 6.00% and schedules payments through 2054. The schedule left to pay holds $19,205,000.00 in principal and $21,216,600.00 in interest.1 The obligation is "secured by Improvement Area #3 Special Assessments on a basis subordinate to the payment of debt service on the Improvement Area #3 2024 Bonds." That wording means the 2024 bonds are paid ahead of the developer.6
What is still owed?
The 2025 plan listed Area #1's outstanding assessment at $3,389,136.89.3 The 2026 plan lists it at $3,173,111.36.1 For Area #2, the 2025 plan listed $4,167,748.79.3 The 2026 plan lists $4,032,642.04.1 The Major Improvement Area stood at $14,464,999.94 in the 2025 plan.3 It is $14,162,826.40 in the 2026 plan.1
The 2025 plan put Area #3's outstanding assessment for the 2024 bonds at $13,047,000.00. Its Area #3 roll listed another $19,447,000.00 for the developer's reimbursement obligation.3 The 2026 plan puts Area #3 at $32,041,969.74. It ties $12,872,882.80 of that to the bonds. It ties another $19,169,086.94 to the developer's reimbursement obligation.1
The 2025 plan put the unpaid Area #1 bonds at $3,450,000.00. It put the unpaid Area #2 bonds at $4,260,000.00.3 The 2026 plan gives no such figure for any bond series. It points readers to the Electronic Municipal Market Access (EMMA) website, where bond information "may be available through continuing disclosure filings."1
What about the reserve?
In Area #2, Area #3, and the Major Improvement Area, part of each bill goes to a reserve for late payments and prepayments.1 The 2025 plan put Area #3's reserve requirement at $717,585.00 and said it "has not been met." It gave the same finding for Area #2, at $234,300.00. It gave the same finding for the Major Improvement Area, at $795,575.00. The plan said the reserve "will be funded with additional interest on the outstanding assessment."3 State law caps an assessment's interest rate at "one-half of one percent higher than the actual interest rate paid on the debt."5 The 2026 plan pages we reviewed do not say whether the requirement has been met. The 2027 Area #3 bill still includes $64,485.00 in additional interest. The Major Improvement Area bill includes $70,875.00.1
Who runs the Tessera pool and park?
The district's public park facilities include about 6,840 feet of hike and bike trails, a 25-space parking lot, a pavilion with restrooms, showers, and a swimming pool. A 2017 agreement says $1.7 million in PID bond money was used to build the park facilities, and the developer had spent or would spend more than $585,000.00 to finish them. It also says the city "has not expended any City funds to construct the Public Park Facilities."10
Under the 2012 development agreement, the developer agreed to pay to build, run, and maintain the public parks. The city agreed to accept the parks "for ownership purposes only," and "The City shall have no obligation at any time to construct, operate or maintain such public parks."10
On June 15, 2017, the council approved Resolution 17-1703, which let the mayor sign an operation and maintenance agreement with the developer and the Tessera homeowners association (HOA). Under that agreement, the HOA runs the facilities "without cost to the City," paying for utilities, trash, the pool, the pavilion, and lifeguards during public hours. The developer funds the HOA's costs until it hands that duty to the HOA. One cost is shared, because if pool equipment or furniture is damaged during public hours, the HOA and the city "will each pay fifty percent."10
The trails, the pavilion, and its restrooms are open to "residents and non-residents of Tessera." The pool is open to the public from Memorial Day weekend to the weekend before the school year starts. Public hours are Sunday through Thursday, 8 a.m. to 11:30 a.m. Swimmers need a pool pass from the city or must pay the city's daily fee.10
On June 5, 2025, the council held a work session on city ownership of the Tessera parkland. It agreed to research whether "the original land transfer could potentially be voided due to the errors" and to have staff work with the developer to correct them.11 As our earlier story reported, on Nov. 6, 2025, the council tabled a resolution that included a correction deed for the pool property.12
On April 16, 2026, Council Member Jess Hall put the Tessera maintenance agreement on a work session agenda. Hall's report said "The HOA is bearing the full cost of lifeguard services during public access hours." It put the cost at about $91.50 an hour for three lifeguards.13 The council directed the city attorney to review the agreement.14 On May 7, 2026, the council took no action on a proposal that the city provide lifeguards during the pool's public hours.15
On May 21, 2026, after a closed session, Council Member Paul Prince moved to direct the city attorney "to send notice of non-renewal to Hines related to the Tessera maintenance agreement."16 Council Member Amanda Chavarria seconded, and the vote was 6-0, with Mayor Shane Saum absent.17 Prince then changed his motion so the city manager would send the letter after the attorney reviewed it.16 The agreement requires such notice "at least twelve months prior" to the end of a term.10
What it means for you
City taxes are not pledged to the 2024 bonds. If an owner does not pay, the 2024 bonds are "special obligations of the City payable solely from the Trust Estate," meaning the pledged assessments and bond accounts.4 Under the 2017 agreement, the HOA runs the pool and park "without cost to the City," and the developer funds the HOA until that duty passes to the HOA. The city pays half the cost to repair or replace pool equipment or furniture damaged during public swim hours.10 The bond ordinance says the city "shall have no legal or moral obligation to pay for the Bonds out of any funds of the City other than Trust Estate."4 The Major Improvement Area's 2020 bonds are "payable solely from the MIA Special Assessments and other funds pledged pursuant to an indenture." For Tessera owners, a late installment faces "the penalties, procedures, and foreclosure sale" used for unpaid property taxes.6
Questions the law raises
Some of these records raise questions under Texas law and federal rules. They are questions, not findings that anyone broke the law.5
Is the developer's 6% under the state cap?
State law caps interest on a reimbursement agreement at "five percent above the highest average index rate for tax-exempt bonds" for up to five years, and at two percent above that index after that.5 The Tessera plan figures the developer's interest at 6.00% for every year of its schedule. The plans we reviewed do not name the bond index or its rate when the obligation began, so we could not test the rate against the cap.1
Should today's owners pay past-due bills?
State law lets assessments pay "expenses incurred in the establishment, administration, and operation of the district."5 The 2025 plan billed Area #3 owners for "Past Due P3Worksc LLC Invoices" without saying what years or work they covered. Whether those costs belonged to earlier years, and so to earlier owners, is the open question.3
Was the 2026 plan filed with the county?
Within seven days of updating a service plan, state law says the city "shall file a copy of the amended or updated plan with the county clerk."5 The copy of the 2025 plan on the city's website carries a Travis County recording stamp dated Aug. 27, 2025.18 The copy of the 2026 plan on the city's website carries no such stamp, and that copy alone does not show whether it was filed.19
Is the reserve full, and would anyone be told?
Last year's plan said three reserves were short of their required size and were being built up from additional interest, and this year's plan is silent on it.13 A federal securities rule has bond issuers promise to post notice of events such as "Unscheduled draws on debt service reserves reflecting financial difficulties."20 The 2026 plan points readers to those filings on EMMA.1
Who runs the pool if the agreement ends?
The 2017 agreement says that because tax-exempt PID bonds paid for the facilities, it "has to comply with the management contract's safe-harbor guidelines" of the Internal Revenue Service.10 The records we reviewed do not say who would run the pool, or on what terms, once the agreement ends.17
How they voted
Present on Aug. 21, 2025, were Mayor Kevin Sullivan, Mayor Pro Tem Rob Durbin, and Council Members Shane Saum, Norma Owen, Paul Roberts, Paul Prince, and Adam Benefield.7 It was a voice vote, and on the video the chair announced it as passing "6 to 1 with Mr. Durbin being the dissenting party."8 From the minutes, which list seven members present and Durbin as the only no vote, we infer the other six voted yes.7 On Aug. 6, 2026, Mayor Shane Saum, Mayor Pro Tem Norma Owen, and Council Members Adam Benefield, Paul Prince, Amanda Chavarria, Karen Van Ness, and Jess Hall voted yes. No one voted against, and the minutes list City Manager Charles West as absent.2
Where it stands
Owners' next installments are due Jan. 31, 2027. The plan says an owner's "sole and exclusive remedy" for an error is a written notice to the administrator by Dec. 1. The council must update the plan again next year.1
What we could not find
- The unpaid principal of each bond series after any early redemptions. The 2026 plan points readers to the Electronic Municipal Market Access (EMMA) website instead.1
- Whether the reserves have reached their required size.1
- What the $58,588.61 in past-due invoices covered, and for what years.3
- Whether the city sent the non-renewal notice, when the pool agreement ends, and who would run and pay for the pool after that.17
- The vote on Resolution 17-1703 in 2017, and whether the city has accepted the correction deed for the pool property.1012
- Whether the 2026 plan was filed with the Travis County clerk.19
- The bond index rate used to set the developer's 6.00% rate.1
- How much the developer has been repaid so far.1
What you can do
- File a Texas Public Information Act request on the city's records page for the P3Works invoices, reserve fund balances, trustee reports, and the park operating agreement.21
- Look up the bonds on EMMA, the Municipal Securities Rulemaking Board's public bond website, which the 2026 plan names.1
- Send a written notice of error to the administrator at admin@p3-works.com by Dec. 1.1
- Find your own lot type's bill in the plan's buyer notices, Exhibit C.1
- Ask the city in the same request for the non-renewal letter to Hines and any reply.21
- Search the Travis County clerk's online records for the 2026 Tessera plan.18
Email alerts
Get the next story by email
We email you when a person has checked a new story against the record and it goes live. No ads, no tracking.
Lago Vista Watchdog is free for everyone. Readers who can pay keep it that way. Become a member.
Podcast transcript
Read the transcript
Host 1. This is the Lago Vista Watchdog briefing. The two voices you are hearing are AI generated. Every fact in this episode is sourced in the full story on our website, and a person validates each story before it is published.
Host 2. Here is the bottom line. This story is about the yearly bills in Tessera's public improvement district, and who pays them. Owners there are scheduled to pay $4,213,564.99 due January 31, 2027.
Host 1. That is $64,692.33 less than the 2025 plan scheduled a year earlier. The City Council approved the 2026 plan by a vote of 7 to 0 on August 6, 2026.
Host 2. Tessera owners pay these bills, not the city's general taxpayers. The district's 2024 bonds can never be repaid from city property taxes or other city money.
Host 1. Now, in order, here is how we got here. First, what is a PID? A public improvement district lets a city fund a project that gives one area a special benefit.
Host 2. Owners in the district pay yearly installments, collected the same way and at the same time as property taxes. The money repays bonds, which are loans from investors, and in one area it also repays the developer.
Host 1. State law requires the council to update the plan every year. The district bills four parts separately, called Improvement Area #1, Area #2, Area #3, and the Major Improvement Area.
Host 2. Our earlier story covered the park-list motions at both meetings and the debate over what buyers are told. This episode compares the dollar figures in the two plans.
Host 1. On August 21, 2025, the council took up the 2025 plan at a regular meeting. For bills due January 31, 2026, that plan set Area #1 at $312,325.40, Area #2 at $356,630.98, Area #3 at $2,488,597.48, and the Major Improvement Area at $1,120,703.46.
Host 2. Together those came to $4,278,257.32. The cover page said there is no financial impact to the city.
Host 1. Mayor Kevin Sullivan moved to approve it, and Council Member Adam Benefield seconded. The motion added a new Exhibit B, a list of park facilities for the notices given to buyers, with two items removed that had not yet been dedicated to the city. It changed no dollar amount.
Host 2. The motion passed 6 to 1, with Mayor Pro Tem Rob Durbin voting no.
Host 1. On August 6, 2026, the council took up the 2026 plan. Its bills for 2027 are $308,311.15 for Area #1, $350,949.17 for Area #2, $2,433,516.59 for Area #3, and $1,120,788.08 for the Major Improvement Area.
Host 2. Mayor Pro Tem Norma Owen moved to approve it, and Council Member Amanda Chavarria seconded. The minutes word the motion as adding attachment B and excluding what has not been approved. It passed 7 to 0.
Host 1. So how did the bills change? The total is 1.5% lower. Area #1 fell by $4,014.25, Area #2 by $5,681.81, and Area #3 by $55,080.89. The Major Improvement Area rose by $84.62.
Host 2. Look at Area #3's administrative costs. The 2025 plan budgeted $105,771.48 for them, including a line of $58,588.61 for past-due invoices from P3Works, the district's administrator.
Host 1. The 2026 plan budgets $50,085.59. That is $55,685.89 less, more than the drop in Area #3's whole bill. The plans we reviewed do not say which invoices were past due.
Host 2. What does one home pay? Every one of the 19 lot types has a smaller bill for 2027 than for 2026.
Host 1. A 40-foot lot in Phase 2 of Area #3 is called Lot Type 14. It was billed $4,799.22 for 2026. Its bill for 2027 is $4,711.43, which is $87.79 less.
Host 2. Over its schedule through 2054, that home's bills add up to $133,966.96. Together, the developer's principal and interest make up 48.2% of that.
Host 2. A 60-foot lot in Phase 2 is called Lot Type 16. Its bill went from $6,126.66 to $6,014.59. In the older Areas #1 and #2, the 2027 bills run from $690.26 to $1,598.23.
Host 1. Who gets the money? The 2027 bills include $1,410,300 for the developer's reimbursement obligation, which repays the developer for costs it paid up front in Area #3. That is 33.5% of the total.
Host 2. The interest on it is 6.00%, with payments scheduled through 2054. The schedule left to pay holds $19,205,000 in principal and $21,216,600 in interest. The 2024 bonds are paid ahead of the developer.
Host 1. As for what is still owed, Area #1's assessment fell from $3,389,136.89 to $3,173,111.36, and the Major Improvement Area's from $14,464,999.94 to $14,162,826.40.
Host 2. The 2026 plan puts Area #3 at $32,041,969.74, of which $12,872,882.80 backs the bonds and $19,169,086.94 backs the developer's obligation.
Host 1. Last year's plan said the reserves for late payments in three areas had not met their required size. This year's plan does not say whether they have. The 2027 Area #3 bill still includes $64,485 in additional interest for that reserve.
Host 1. What about the Tessera pool and park? A 2017 agreement says $1.7 million in PID bond money was used to build them, and the city spent none of its own money building them.
Host 2. Under that agreement, the homeowners association runs them without cost to the city, and the developer funds its costs. The city pays half the cost to repair or replace pool equipment or furniture damaged during public swim hours.
Host 1. Anyone can use the trails and the pavilion. The pool is open to the public Sunday through Thursday, 8 a.m. to 11:30 a.m., from Memorial Day weekend until school starts, with a city pool pass or the city's daily fee.
Host 2. On May 21, 2026, the council voted 6 to 0 to send notice that it would not renew that agreement. The records we reviewed do not say who would run the pool after it ends.
Host 1. The records also raise questions, not findings. State law caps interest on a developer reimbursement against a bond index. The plans we reviewed do not name that index, so we could not test the 6.00% rate.
Host 2. The 2025 plan billed owners for past-due administrator invoices without saying what years they covered. And the 2026 plan the city posted carries no county recording stamp, while last year's copy does.
Host 2. What does it mean for you? For city taxpayers, city taxes are not pledged to the 2024 bonds, and the bond ordinance says the city has no legal or moral obligation to pay them from other city funds.
Host 1. If you own in Tessera, a late installment faces the same penalties and foreclosure sale used for unpaid property taxes. The plans we reviewed do not say who pays to run the Tessera pool and park.
Host 2. How can you weigh in? If you think your assessment has an error, the plan says to send written notice to the administrator by December 1. You can find your lot type's bill in the plan's buyer notices.
Host 1. You can also file a public records request with the city for the P3Works invoices and the reserve balances, and look up the bonds on the Electronic Municipal Market Access website. Thanks for listening to the Lago Vista Watchdog.
Sources and documents
Every fact in this story comes from the records below. The small numbers in the story point to them. Links go to the exact moment in the meeting video or the page in the document.
- City Council agenda packet, Aug. 6, 2026, item XII.5 cover page and draft Tessera 2026 Annual Service Plan Update See p. 198.
- City Council regular meeting minutes, Aug. 6, 2026, Tessera 2026 Annual Service Plan Update See p. 9.
- City Council agenda packet, Aug. 21, 2025, item 11A cover page and Tessera 2025 Annual Service Plan Update See p. 92.
- Ordinance No. 24-01-04-03, $13,190,000 Special Assessment Revenue Bonds, Series 2024 (Tessera Improvement Area #3), Jan. 4, 2024
- Texas Local Government Code, Chapter 372, Improvement Districts in Municipalities and Counties
- Ordinance No. 24-01-04-02, Tessera Improvement Area #3 assessments and 2024 Amended and Restated Service and Assessment Plan, Jan. 4, 2024
- City Council regular meeting minutes, Aug. 21, 2025, item 11A, Ordinance 25-08-21-01 See p. 6.
- City Council meeting video, Aug. 21, 2025, item 11A, the Exhibit B motion, the removal of items A and C, and the 6-1 vote At 2:36:52.
- City Council meeting video, Aug. 6, 2026, item XII.5, Tessera PID 2026 Annual Service Plan Update, attachment B discussion, motion and vote At 5:53:21.
- City Council agenda packet, April 17, 2025, work session item 3 on Tessera parkland: Resolution 17-1703 (June 15, 2017), the Agreement for Public Park Facilities Operation and Maintenance Services with its Pool Rules, and the 2012 Restated Development Agreement, Sec. 4.05 See p. 27.
- City Council regular meeting minutes, June 5, 2025, work session on city ownership of the Tessera parkland dedication
- City Council regular meeting minutes, Nov. 6, 2025, Resolution No. 25-2164 (Tessera parkland dedication and pool correction deed), tabled
- City Council agenda packet, April 16, 2026, work session item XI.2, Discussion regarding the Tessera Maintenance Agreement, submitted by Council Member Jess Hall See p. 297.
- City Council regular meeting minutes, April 16, 2026, work session on the Tessera Maintenance Agreement
- City Council regular meeting minutes, May 7, 2026, closed session on the Tessera Maintenance Agreement and item 4 on city lifeguards at the Lakeside at Tessera pool
- City Council meeting video, May 21, 2026, the motion to send notice of non-renewal of the Tessera maintenance agreement At 0:06:29.
- City Council regular meeting minutes, May 21, 2026, closed-session item 4 and the 6-0 vote on non-renewal to Hines, Tessera
- Ordinance No. 25-08-21-01, Tessera 2025 Annual Service Plan Update, as signed and recorded (Travis County document 2025095352, filed Aug. 27, 2025)
- Ordinance No. 26-08-06-01, Tessera 2026 Annual Service Plan Update, as posted on the city website
- U.S. Securities and Exchange Commission Rule 15c2-12 (17 CFR 240.15c2-12), municipal securities disclosure
- City of Lago Vista, Open Records Request page
See something wrong? Request a correction. Have records on this? Share them with us.