Council meeting
Lago Vista cuts Garver sewer deal, taxpayer share $476,477.80
The council voted unanimously Nov. 5 to cut the Garver sewer plant deal to $1,573,768.10. A federal grant pays most new design work. The city pays $476,477.80.
The Lago Vista City Council voted unanimously on Nov. 5, 2026, to shrink its sewer plant engineering contract with Garver, LLC to $1,573,768.10.12 The change ends the design for a bigger plant and drops $1,248,133.90 the city would no longer owe. A federal Environmental Protection Agency (EPA) grant pays up to $488,799.20 of the new design work. The city's own share is $476,477.80, its $122,199.80 grant match plus $354,278.00 for construction oversight that the grant does not cover. Staff recommend paying it from 2024 bond money, utility reserves, or both, once balances are confirmed.3 That bond money is city debt that property taxes repay, with a limited pledge of water and sewer revenue.4
Listen
AI voices
A two-host briefing. The voices are AI generated. Read the transcript.

When we wrote this story, the city had not posted minutes for this meeting. This story is based on the meeting video.5
What is the Garver contract?
Garver, LLC is the engineering firm the city hired to design work at its wastewater treatment plant. The old plan was to grow the plant from 1.0 million gallons a day (MGD) to 1.5 MGD. The contract has a not-to-exceed amount, which is the most the city can owe the firm. The council votes on this change, and then the city manager signs it.3
The new total has two parts. The grant and the city's share cover $965,277.00 in new work. The other $608,491.10 is what Garver had already billed for the old design.3
Our Nov. 2 preview of this vote found that the amendment drops the bigger plant and points the grant at new filters and a new sludge press.3 That story also told how the contract began in December 2024 at no more than $2,821,902.00.6
Victor Manzano, the city's capital improvement plan (CIP) manager, submitted the item.3 The council took it up at its regular meeting in the City Council Chambers, 5803 Thunderbird. The meeting began at 3 p.m., and the open session was set to start again at 4 p.m. after a closed session.7
The council heard three other water items at the same meeting. We cover them in separate stories on the state loan, the effluent study, and the EPA grant split.8
The presentation
Mayor Shane Saum read the Garver item aloud together with the other three.78 He said, "They're all water related."8
Public Works Director Ernesto Rios then gave a slide presentation.9 The city won a $750,000 EPA Community Grant on Sept. 22, 2026, for planning and design at the plant and for handling its treated wastewater. The grant requires the city to add $187,500, for a total of $937,500. EPA money can pay only for planning, permitting, design, and bidding work.10
Rios said staff propose splitting the grant between two engineering jobs. One is the Garver work.9 The other is a study by a second engineering firm (DCS Engineering, LLC) of how the city handles its treated wastewater.79
A council member asked whether 2024 bond money would pay for some of this. Rios said it was not, for now. Manzano called it "a pending decision."11
Manzano said the plant work no longer qualifies for wastewater impact fees because the city is no longer adding capacity.11 Under state law, an impact fee is a charge on new development to pay for the capital projects that growth makes necessary.12
The mayor asked why the project was moving away from the city's 2024 wastewater master plan.13 He suggested that Freese and Nichols, the engineers who wrote that plan, come back and talk with staff to check whether "this is the right route to go."1314
Rios said the amendment removes the 1.5 MGD expansion and moves two fixes forward, as our preview explained.15 A council member asked how much of the bigger-plant design had been abandoned. Rios answered, "It has not been abandoned."16
Council Member Jess Hall said he was concerned about paying for more planning before the city handles "the immediate needs that are before us right now." He named repairs at Pond 17, Pond 14, and the Cedar Breaks pond.17
What Garver said
The mayor asked whether anyone in the audience wanted to speak on the four items, and no one did.18 Mayor Pro Tem Norma Owen then asked Garver to walk the council through its work from the start.719
Jeff Meadows, a treatment lead at Garver, said the firm got "just short of 30% design" on the bigger plant before the city put it on hold. He said that work "is not all abandoned." Garver finished a permit change with the Texas Commission on Environmental Quality (TCEQ), the state environmental agency, that lets the plant grow to 1.5 MGD later. He said the state first wanted 20 million to 30 million more gallons of pond storage, and Garver showed that the ponds the city has now are enough.20
Meadows said the site survey and soil tests carry over to the new design. Meadows said Garver worked with city staff and visited plants in Kyle, Huntsville, and Pflugerville before choosing a volute press. He said the city owns the report, so it "can pick up where they left off" if it returns to the expansion.20
Hall said he would love to see the belt press replaced and a move to Type I water.21 Under state rules, Type I reclaimed water is treated wastewater clean enough for places where the public may touch it, such as parks and home lawns.22 Hall said he wanted those pieces to move forward "without necessarily obligating the city" for "a sizable loan" it would have to repay.21
An engineer for Garver answered that those two items are the ones moving forward, and "everything else was removed and stripped out of the scope."23 A staff member added that the grant pays for design and planning, and the proposed state loan would pay for construction. For the plant work before the council at this meeting, the staff member said, the city's part would come from the bonds or from utility money.24
Timing and the old press
The Garver engineer said the current ponds are enough until the plant reaches 1.5 MGD. He said city staff found that the plant's flows had leveled off. He said the last time it came up, the need to expand looked to be "past 2030 at this point."25
The mayor said he did not want a future council telling this one, "You had your chance to expand when you needed to."26 The engineer said the new filters would treat 1 MGD now and be built so they can grow to 1.5 MGD and later 2.7 MGD.27 He said Garver would work out filter prices with the maker ahead of time, so the price does not jump on bid day.28
The plant's belt press squeezes sewage sludge between two belts to wring out the water, the engineer said. A volute press uses a turning screw that lifts the solids while the water drains away.29 The engineer said design would take at most six months.30
The mayor called the old belt press "a ticking time bomb." After bids, the engineer said, buying and installing the new press would probably take 6 to 8 months. Garver would also help the city find a rental press on a trailer. He expects that to cost less than hauling away wet sludge when the old press breaks down.30 Council Member Amanda Chavarria said she was "really impressed" with the choice of the volute press.31
The vote
Before any motion, the mayor said, "I am comfortable now with the Garver one."32 Council Member Adam Benefield said he was not comfortable moving forward on either the Garver amendment or the effluent study that day. He said, "I've seen too much waste on these designs." The mayor noted the council meets again on Nov. 19.33
The council then approved the state loan papers by voice vote.34 Next, a motion to approve the effluent study failed 3 to 4.3536 Before the Garver vote, a council member asked staff to explain to the whole council why bond money is being used and what limits apply to impact fees.37
Council Member Paul Prince then moved to approve the Garver amendment, item VIII.2. He said the need for it had been "laid out pretty well."1 Council Member Karen Van Ness seconded.38
Chavarria said she would normally vote against it without more information. But she said she wanted the press work started "as quickly as possible."39 Prince noted that the amendment lowers the contract, calling it "a reduction in spend on the city's part."40
The mayor called the roll. Hall answered, "I move approval." Benefield, Chavarria, the Mayor Pro Tem, Van Ness, and Prince each said yes, and the mayor said he was also a yes.2 Benefield's yes came after he had said he was not comfortable moving forward, though he had added that his mind could be changed.233 The mayor said, "It's approved unanimously."2
What it means for you
Which fund pays the city's share is still open. The packet says the city-funded part is "subject to confirmation of available balances and final budget allocation." Staff no longer recommend using wastewater impact fees for this work.3 Yet the adopted 2026-27 budget still lists $820,000 in wastewater impact fees as the source for this project's design work this year. The budget page calls those amounts planning placeholders, to be updated as staff works with the engineer on the design amendment, final scope, and costs.41 If bond money pays, property taxes repay that debt.4
What we could not find
- Minutes with each member's vote. The city had not posted minutes when we wrote this.5
- Which fund will pay the city's $476,477.80, and the current balances of the 2024 bond money and the utility reserves.3
- A city record that says what "Utility Reserves" holds and where it comes from.3
- Staff's written reason that wastewater impact fees no longer apply.37
- The revised EPA grant workplan, which the packet says is due to the EPA by Nov. 12, 2026.10
- A construction cost for the filters and the new press alone.3 The budget shows only a $9,000,000 planning placeholder for construction on the whole plant project.41
- What Garver has billed since Aug. 29, 2025, the last invoice the amendment names.3
What you can do
Email alerts
Get the next story by email
We email you when a person has checked a new story against the record and it goes live. No ads, no tracking.
Lago Vista Watchdog is free for everyone. Readers who can pay keep it that way. Become a member.
Podcast transcript
Read the transcript
Host 1. Welcome to the Lago Vista Watchdog podcast. The two voices you're hearing are AI generated, and every fact comes from a public record.
Host 2. Today we're looking at the sewer plant engineering contract the City Council cut back on Nov. 5, 2026.
Host 1. Here's the bottom line. The council voted unanimously to shrink its contract with the engineering firm Garver to $1,573,768.10.
Host 2. That ends the design for a bigger plant, and it drops $1,248,133.90 the city would no longer owe.
Host 1. A federal grant from the Environmental Protection Agency pays up to $488,799.20 of the new design work. The city's own share is $476,477.80.
Host 2. And where does that share come from?
Host 1. That's still open. Staff recommend 2024 bond money, utility reserves, or both, once balances are confirmed. Property taxes repay that bond money.
Host 2. One more thing before we start. When we wrote this story, the city had not posted minutes for this meeting, so everything here comes from the meeting video.
Host 1. So, a quick catch-up for anyone new. Garver is the firm the city hired to design work at its wastewater treatment plant. The old plan was to grow the plant from 1.0 million gallons a day to 1.5.
Host 2. Our Nov. 2 preview walked through the change. The bigger plant comes out, and the grant goes toward new filters and a new press for sewage sludge.
Host 1. The council heard this item together with three other water items, which we cover in separate stories.
Host 2. Public Works Director Ernesto Rios opened with a slide presentation. The city won a $750,000 grant on Sept. 22, and it has to add $187,500 of its own.
Host 1. A council member asked whether 2024 bond money would pay for some of this. Victor Manzano, who manages the city's capital projects, called that a pending decision.
Host 2. He also said the plant work no longer qualifies for impact fees, the charges new development pays toward growth, because the city is not adding capacity.
Host 1. The mayor wanted to know why the project was drifting from the city's 2024 wastewater master plan. He suggested the engineers who wrote that plan come back and check the new route with staff.
Host 2. Council Member Jess Hall raised a different worry. He wanted the city to handle needs it already has, like repairs at Pond 17, Pond 14, and the Cedar Breaks pond, before paying for more planning.
Host 1. Then Garver got its turn. Jeff Meadows, a treatment lead with the firm, said Garver reached just short of 30% design on the bigger plant before the city put it on hold.
Host 2. He told the council that work is not all abandoned. Garver finished a state permit change that lets the plant grow to 1.5 later, and showed the ponds the city has now are enough.
Host 1. The site survey and soil tests carry over too. And the firm worked with city staff and visited plants in Kyle, Huntsville, and Pflugerville before choosing a volute press.
Host 2. Hall said he'd love to see the press replaced and the move to cleaner reuse water. He just didn't want to tie the city to a big loan it would have to repay.
Host 1. The Garver engineer said those two pieces are the ones moving forward, and everything else was stripped out.
Host 2. And when might the plant actually need to grow?
Host 1. He said city staff found the plant's flows had leveled off. The last time it came up, the need to expand looked to be past 2030.
Host 2. What's a volute press?
Host 1. The old belt press squeezes sludge between two belts to wring out the water. A volute press uses a turning screw that lifts the solids while the water drains away.
Host 1. Design could take up to six months, the engineer said.
Host 2. The mayor called the old belt press a ticking time bomb.
Host 1. After bids, buying and installing the new press would probably take 6 to 8 months more.
Host 2. Garver would also help the city rent a press on a trailer, which he expects to cost less than hauling away wet sludge when the old one breaks down.
Host 1. Now the vote. Before any motion, the mayor said he was comfortable with the Garver item.
Host 2. Council Member Adam Benefield was not. He said, "I've seen too much waste on these designs."
Host 1. The council approved the state loan papers, and a separate study of the city's treated wastewater failed 3 to 4.
Host 2. Then Council Member Paul Prince moved to approve the Garver change, and Council Member Karen Van Ness seconded. Prince pointed out it lowers the contract.
Host 1. The mayor called the roll. Council Member Hall answered that he moved approval. Every other member said yes, Benefield included, and the mayor announced it passed unanimously.
Host 2. So what does it mean for you?
Host 1. Staff no longer recommend impact fees for this work. Yet the adopted budget still lists $820,000 in impact fees for this project's design this year, though the budget calls those figures placeholders.
Host 2. If bond money pays the city's share, property taxpayers carry it. The council meets again Nov. 19.
Host 1. You can watch the motion and the vote in the city's meeting video. And you can ask the city for the revised grant workplan and the bond balance through its records request page.
Host 2. Thanks for listening to the Lago Vista Watchdog.
Sources and documents
Every fact in this story comes from the records below. The small numbers in the story point to them. Links go to the exact moment in the meeting video or the page in the document.
- City Council meeting video, Nov. 5, 2026 (Council Member Prince moves to approve item VIII.2) At 1:49:00.
- City Council meeting video, Nov. 5, 2026 (roll call vote on item VIII.2) At 1:50:35.
- City Council agenda packet, Nov. 5, 2026, item VIII.2 and Contract Amendment No. 2 with Garver, LLC See p. 13.
- City Council agenda packet, Jan. 18, 2024, certificates of obligation item See p. 21.
- City of Lago Vista meeting list on Granicus, checked Nov. 5, 2026 (the Nov. 5 meeting lists an agenda and packet, no minutes)
- City Council minutes, Dec. 5, 2024
- City Council regular meeting agenda, Nov. 5, 2026
- City Council meeting video, Nov. 5, 2026 (the mayor reads items VIII.1, VIII.2, VIII.3, and IX.9 together) At 0:18:46.
- City Council meeting video, Nov. 5, 2026 (Public Works Director Ernesto Rios presents the EPA grant split) At 0:20:36.
- City Council agenda packet, Nov. 5, 2026, item IX.9 and the EPA Community Grant funding allocation summary See p. 94.
- City Council meeting video, Nov. 5, 2026 (a question on 2024 bond money and wastewater impact fees) At 0:25:54.
- Texas Local Government Code, Chapter 395, Sec. 395.001 (definition of impact fee)
- City Council meeting video, Nov. 5, 2026 (the mayor asks why the project is changing from the 2024 master plan) At 0:26:46.
- City Council minutes, April 18, 2024 (Final Wastewater Master Plan, Freese and Nichols) See p. 5.
- City Council meeting video, Nov. 5, 2026 (Rios explains Contract Amendment No. 2) At 0:28:35.
- City Council meeting video, Nov. 5, 2026 (a question on what design work was abandoned) At 0:30:23.
- City Council meeting video, Nov. 5, 2026 (Council Member Hall on immediate needs) At 0:36:06.
- City Council meeting video, Nov. 5, 2026 (the mayor asks for public comment) At 0:51:20.
- City Council meeting video, Nov. 5, 2026 (the Mayor Pro Tem asks Garver to explain its work) At 0:51:29.
- City Council meeting video, Nov. 5, 2026 (Jeff Meadows of Garver on the work done so far) At 0:52:20.
- City Council meeting video, Nov. 5, 2026 (Council Member Hall on obligating the city) At 0:55:26.
- Texas Administrative Code, Title 30, Sec. 210.32, Specific Uses of Reclaimed Water (Type I)
- City Council meeting video, Nov. 5, 2026 (Meadows on what the revised scope keeps) At 0:56:38.
- City Council meeting video, Nov. 5, 2026 (staff on what the grant and the loan would pay for) At 0:57:05.
- City Council meeting video, Nov. 5, 2026 (capacity, pond storage, and when the plant may need to grow) At 0:57:48.
- City Council meeting video, Nov. 5, 2026 (the mayor on the risk of waiting to expand) At 1:02:13.
- City Council meeting video, Nov. 5, 2026 (Meadows on building the filters to expand later) At 1:02:25.
- City Council meeting video, Nov. 5, 2026 (Meadows on pre-negotiating filter prices) At 1:03:05.
- City Council meeting video, Nov. 5, 2026 (Meadows on how a volute press works) At 1:06:42.
- City Council meeting video, Nov. 5, 2026 (design and installation timeline and rental presses) At 1:07:38.
- City Council meeting video, Nov. 5, 2026 (Council Member Chavarria on the volute press) At 1:09:33.
- City Council meeting video, Nov. 5, 2026 (the mayor says where he stands on each item) At 1:11:00.
- City Council meeting video, Nov. 5, 2026 (Council Member Benefield on design spending) At 1:11:39.
- City Council meeting video, Nov. 5, 2026 (voice vote on the state loan resolutions (item VIII.3)) At 1:39:57.
- City Council meeting video, Nov. 5, 2026 (roll call vote on item VIII.1, the effluent study) At 1:44:27.
- City Council meeting video, Nov. 5, 2026 (the mayor announces the item VIII.1 result) At 1:48:05.
- City Council meeting video, Nov. 5, 2026 (Council Member Chavarria asks staff about impact fees) At 1:47:07.
- City Council meeting video, Nov. 5, 2026 (the second on item VIII.2) At 1:49:37.
- City Council meeting video, Nov. 5, 2026 (Council Member Chavarria before the vote) At 1:49:52.
- City Council meeting video, Nov. 5, 2026 (Council Member Prince on the lower contract amount) At 1:50:17.
- City of Lago Vista 2026-27 budget, capital improvement plan page for WWTP Improvements See p. 172.
- City of Lago Vista open records request page
See something wrong? Request a correction. Have records on this? Share them with us.